The London North Pole depot is one of three depots selected by Hitachi to house its new fleet of long-distance intercity express trains that will operate on the Great Western Mainline (GWML). The depot had been dormant since 2005 and required significant re-configuration and refurbishment to meet Hitachi’s needs, including creating two new connections to the GWML.
VolkerFitzpatrick was appointed as principal contractor to deliver the key facilities needed. To support the timely construction of the depot experienced JBA Rail project managers were engaged to help meet the deliverables. These included the main servicing shed, a 400m long, six track shed for light maintenance and cleaning and a repair shed approximately 200m long with four tracks, to carry out major repairs. We also delivered a dedicated wheel lathe building to re-profile wheels and an additional bogie shed that will primarily be used for single bogie changes.
A range of specialist cleaning and servicing equipment was also installed, including a train washing machine, toilet emptying facilities and water replenishment equipment.
A new 60m long bridge, constructed in only 16 weeks, carries the access road over the port's new railway, connecting the southern and northern parts of the port development.
To address poor ground conditions, the bridge was constructed on DCIS piled foundations to achieve the high working load tolerances required in weak subsoil conditions. Due to the bridge span being within 16m of a non-load bearing sea wall, we developed a bespoke bridge embankment solution. This was constructed using lightweight polystyrene fill combined with an 86m long 'skinny' facing wall.
JBA achieved a reduction in planned and unplanned work hours between ship 1 and ship 2 in the structures area of 40-45% as opposed to the business expectations of 25%. This reduced the production time from 7 weeks to 4 weeks bringing the milestone payment back on schedule.
JBA set up a modern, state-of-the-art control centre that coordinated our response to incidents in service, failures and provided a route to short-term mitigations and long-term solutions to prevent re-occurrence. We also for once had a real time visibility of our resources and the competence of staff.
With the assistance of JBA, we managed to resolve recurring issues, resulting in reducing financial penalties to our customers by 3.6 million year on year.
Having the knowledge of what to do should a risk occur, as opposed to losing valuable time in crisis management proved invaluable in ensuring the Program was delivered on time and to budget - a fantastic system which we will continue to use.
The results go to show that JBA achieved their project brief very successfully...Excellent communication and involvement throughout the process.
In my 35 years of working for New York City Transit, JBA are the first consultants who truly understood our business, implemented real change and delivered sustainable results.
JBA were a valuable part of 2008 Formula 1 World Championship winning team.
The railway operator set a deadline to find a solution within 3 months. The solution was identified and implemented on the fleet within 6 weeks. JBA were able to integrate technical and organisational expertise to exceed customer expectations.
History in words
Initially to provide hands-on consultancy services primarily within the rail industry, the primary clients being London Underground (LUL), Network Rail, Metro trains Melbourne, Sydney Trains, Bombardier Transportation, Metronet Rail, BVT Surface Fleet and BAE Surface Ships , where a variety of roles were undertaken from interim operation management, supply chain management, engineering management to COO and Vice President of Operations Performance.
Currently JBA are working with various Rail Organizations in the US to devise methods of consultant support to improve their business performance. JBA Change Management Corporation (North America) was set up June 2017 to establish a firm base for all contracts in the US going forward and to provide a presence in the North American market.